Project Status

Follow these steps to check the translation status of your projects.
  1. In Projects view, select the project that you want to examine.
  2. In main menu, select ProjectsProject Status or click the status.svgProject Status button in the Projects view toolbar.
The Project Status dialog appears:
Project Status dialog Status view
The Status column shows the current translation state for all target languages. Possible values are:
  • Untranslated: no XLIFF file has been generated yet for the target language.
  • In Progress: an XLIFF file has been generated for the language and the translated version has not been imported yet.
  • Completed: the last XLIFF file generated for the target language has been imported.
You can mark one or more languages as completed by selecting the corresponding check boxes and clicking the Mark Selection as Translated button.
Click the Project History tab to display a list of events associated with the project.
Project Status dialog, History view
Select the check box of an XLIFF Created event to discard one or more XLIFF files that have not been imported yet and click the Cancel Selected XLIFF Files buton to adjust project status accordingly.